Hi folks -
This behavior seems to be new for 2007 - does anyone know if there is a way
to disable it by default without having impacts on other aspects of the
product:
If you import a schedule (in XML format) that has tasks that are fixed
duration with resources assigned at 0%, MSP 2007 changes them to a 0-day
duration milestone.
In MSP 2003 and before, there was no changes made to the milestone status or
to the duration of the tasks.
Thanks!
Kiron