A
Andrew Parish
I know that the general advice around multiple resources is "don't". I'm
hoping that if I describe the scenario I'm struggling with, someone can
point me at a better way of doing it.
Consider a task that will require 21 days of effort. I have 3 resources that
have the skills that can be applied to the task - lets call them A, B and C.
A has 100% availability, B has 50% availability and C has 75% availability.
Project quite rightly assigns 9.33 days of effort to A, 4.67 days to B, and
7 to C.
Now, C is sick couple of days which are duly blocked out in his resource
calendar. This has the effect of extending the duration of the task to take
into account what is he needs to complete his share of the task. In reality,
those 2 days could be undertaken by A and B once they've finished their
share and I'd end up with resources that are used to 100% of their
availability; in practice, according to Project at least, I'll have a
couple of people waiting around for C to finish his work before they can all
start on the next task.
What I'm hoping that Project can do for me is take all of this into account,
load everyone up as fully as possible to schedule the task to be completed
in the shortest amount of time.
Am I fighting a losing battle, or is there a way that this can be achieved?
Thanks in advance for any advice.
Andy
hoping that if I describe the scenario I'm struggling with, someone can
point me at a better way of doing it.
Consider a task that will require 21 days of effort. I have 3 resources that
have the skills that can be applied to the task - lets call them A, B and C.
A has 100% availability, B has 50% availability and C has 75% availability.
Project quite rightly assigns 9.33 days of effort to A, 4.67 days to B, and
7 to C.
Now, C is sick couple of days which are duly blocked out in his resource
calendar. This has the effect of extending the duration of the task to take
into account what is he needs to complete his share of the task. In reality,
those 2 days could be undertaken by A and B once they've finished their
share and I'd end up with resources that are used to 100% of their
availability; in practice, according to Project at least, I'll have a
couple of people waiting around for C to finish his work before they can all
start on the next task.
What I'm hoping that Project can do for me is take all of this into account,
load everyone up as fully as possible to schedule the task to be completed
in the shortest amount of time.
Am I fighting a losing battle, or is there a way that this can be achieved?
Thanks in advance for any advice.
Andy