P
Pat Fitzgerald
I need to have cost (resource and task) calcuated in both US Dollars and
Pounds Sterling.
I have my project set in US Dollars with 3 different cost rate tables
available for each enterprise resource. The cost rate tables are in
dollars/hr. I created a custom Resource Cost field in Cost1 called Cost (£)
that multiplies the regular Cost field by .45 to get Cost in pounds.
I also created a custom Task Cost field. When I view my project in task
usage, Task Usage / Table: Cost and add in the Cost (£) field, it shows up
and is calculated correctly. But it does not show up in Resource Usage /
Table: Cost.
Any help would be appreciated.
Pounds Sterling.
I have my project set in US Dollars with 3 different cost rate tables
available for each enterprise resource. The cost rate tables are in
dollars/hr. I created a custom Resource Cost field in Cost1 called Cost (£)
that multiplies the regular Cost field by .45 to get Cost in pounds.
I also created a custom Task Cost field. When I view my project in task
usage, Task Usage / Table: Cost and add in the Cost (£) field, it shows up
and is calculated correctly. But it does not show up in Resource Usage /
Table: Cost.
Any help would be appreciated.