L
ljohnson0406
I need to track REAL % complete of tasks as of a status date, and need MS
Project to recalculate remaining days based on this % complete. For example,
if I have 10 days to build a wall, but after 2 days (status date) I am 50%
finished building the wall, I want to capture:
Actual Start Date
% Complete = 50%
Remaining Days = 2 days (since it took 2 days to finish the first 50%, not 5
days)
Someone PLEASE help! I don't want % complete and Remaining days to be based
on a fixed duration.
Thanks,
LJ
Project to recalculate remaining days based on this % complete. For example,
if I have 10 days to build a wall, but after 2 days (status date) I am 50%
finished building the wall, I want to capture:
Actual Start Date
% Complete = 50%
Remaining Days = 2 days (since it took 2 days to finish the first 50%, not 5
days)
Someone PLEASE help! I don't want % complete and Remaining days to be based
on a fixed duration.
Thanks,
LJ