How do I create a bar styles an item that isn't already listed? For example
I added a column Duration 1. How do I give that a bar style?
I also see, for example, Progess in Bar Styles is related to Actual
Duration, it seems already programmed but how do you customize that; how does
MSP know Progress is for Actual Duration?
 
R

Rod Gill

Actual Duration / Duration is the definition for % complete as Actual
Work/Work is the definition for % Work Complete.

To create a new bar, select Format Bar Styles then create your bar.
Duration1 doesn't mean anything on its own so use the Start or Start1to 10
and Finish or Finish1-10 or relevant Baseline Start and finish to define
from and to dates.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




koolkat said:
How do I create a bar styles an item that isn't already listed? For
example
I added a column Duration 1. How do I give that a bar style?
I also see, for example, Progess in Bar Styles is related to Actual
Duration, it seems already programmed but how do you customize that; how
does
MSP know Progress is for Actual Duration?

__________ Information from ESET Smart Security, version of virus
signature database 4577 (20091105) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4577 (20091105) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top