K
keithy
I am setting up a project that requires me to assisn one resource to multiple
tasks (in chronological order), with different % of assigned work and set
durations:
IE
Resource = Sam( works on 4 projects at the same time)
Project 1-
task 1) 120 man hour task, 20days to finish, 3/1-3/29, 75% work output,
(meaning he can work on the task only 75% of the time)
task 2) 60 man hour task 15day to finish , 3/29-4/19 50% work output
task 3) 20 man hour task 10day to finish, 4/19-5-3 25% work output
Projects 2,3,4
same idea different start dates
Ultimaltey, I want to track the daily work hours to make sure I'm not
overallocating the resource.
My problem is that I cannot get the "days to finish" to match up with the
actual working dates and total number of hours to be worked. The project is
highly deadline driven and I cannot change the # of working hours or the
dates.
Hope this makes sense
Thanks
keith
tasks (in chronological order), with different % of assigned work and set
durations:
IE
Resource = Sam( works on 4 projects at the same time)
Project 1-
task 1) 120 man hour task, 20days to finish, 3/1-3/29, 75% work output,
(meaning he can work on the task only 75% of the time)
task 2) 60 man hour task 15day to finish , 3/29-4/19 50% work output
task 3) 20 man hour task 10day to finish, 4/19-5-3 25% work output
Projects 2,3,4
same idea different start dates
Ultimaltey, I want to track the daily work hours to make sure I'm not
overallocating the resource.
My problem is that I cannot get the "days to finish" to match up with the
actual working dates and total number of hours to be worked. The project is
highly deadline driven and I cannot change the # of working hours or the
dates.
Hope this makes sense
Thanks
keith