T
Thomas V
Hi,
I've come across a situation where automated resource leveling is
causing under allocations and unnecessary long schedules.
Here's an example:
Project setup: work day=8h; 2 resources 100% available; 1 resource
(Clarice) 50% available
Create 3 tasks and one milestone
- milestone1: project start
- task1: work=40hrs, duration=5d, predecessor=milestone1; resource=Tim
- task2: work=40hrs, duration=5d, predecessor task1;
resource=John[50%], Clarice[50%]
- task3: work=160hrs, no duration set, predecessor milestone 1;
resource=John
If you run automatic leveling on the above task3 will be split so that
john and Clarice can work on taks2 when Tim is done with Task1. The
leveling will not however ensure that John is working full time and
thus cause the schedule to push out unnecessarily.
Is there any way to solve this, sort of manually changing the work
contour? The reason I prefer not doing this is that any future
automatic leveling will cause issues with the contour.
Thanks.
I've come across a situation where automated resource leveling is
causing under allocations and unnecessary long schedules.
Here's an example:
Project setup: work day=8h; 2 resources 100% available; 1 resource
(Clarice) 50% available
Create 3 tasks and one milestone
- milestone1: project start
- task1: work=40hrs, duration=5d, predecessor=milestone1; resource=Tim
- task2: work=40hrs, duration=5d, predecessor task1;
resource=John[50%], Clarice[50%]
- task3: work=160hrs, no duration set, predecessor milestone 1;
resource=John
If you run automatic leveling on the above task3 will be split so that
john and Clarice can work on taks2 when Tim is done with Task1. The
leveling will not however ensure that John is working full time and
thus cause the schedule to push out unnecessarily.
Is there any way to solve this, sort of manually changing the work
contour? The reason I prefer not doing this is that any future
automatic leveling will cause issues with the contour.
Thanks.