Within the enterprise solution, what is the typical method used to
account for setting up resources for a per use cost. The issue I am
contemplating is this.
Say I have a web develpoer on one project that I can get to complete
project for $5000.00. Another project uses a web developer but the
cost is $8000.00. Granted I could assign 5 cost rates in the table but
what happens after those are used up. Because this is an enterprise
resource, project lets me change the rate in my open project but
refuses to keep the rate when I save and close. It uses the cost in
the rate table.
Any suggestions/solution as to how to handle this?
account for setting up resources for a per use cost. The issue I am
contemplating is this.
Say I have a web develpoer on one project that I can get to complete
project for $5000.00. Another project uses a web developer but the
cost is $8000.00. Granted I could assign 5 cost rates in the table but
what happens after those are used up. Because this is an enterprise
resource, project lets me change the rate in my open project but
refuses to keep the rate when I save and close. It uses the cost in
the rate table.
Any suggestions/solution as to how to handle this?