Overallocation of resources

Discussion in 'Project' started by Helenlf, Nov 27, 2014.

  1. Helenlf

    Helenlf

    Joined:
    Nov 27, 2014
    Messages:
    1
    Likes Received:
    0
    Project has just let me increase the resources on two tasks, even though I have not got the resources available. It is not showing up an overallocation.

    eg task 1 - 2 resources
    Task 2 - 2 resources

    Task 1 and Task 2 are have a start to start constraint.

    I then increased those resources to 4 per task, even though I only have 4 resources to use. This should be an overallocation, but it is not showing. Have I managed to override the allocation somehow.
     
    Helenlf, Nov 27, 2014
    #1
    1. Advertisements

  2. Helenlf

    babu

    Joined:
    Jan 16, 2015
    Messages:
    1
    Likes Received:
    0
    babu, Jan 16, 2015
    #2
    1. Advertisements

Want to reply to this thread or ask your own question?

It takes just 2 minutes to sign up (and it's free!). Just click the sign up button to choose a username and then you can ask your own questions on the forum.
Similar Threads
  1. Sbancroft
    Replies:
    0
    Views:
    569
    Sbancroft
    Apr 12, 2012
  2. jasondjhc

    Allocatind Resources using groups

    jasondjhc, Jul 26, 2013, in forum: Project
    Replies:
    0
    Views:
    646
    jasondjhc
    Jul 26, 2013
  3. Achira

    How to tracking Resources?

    Achira, Feb 23, 2016, in forum: Project
    Replies:
    1
    Views:
    221
    Achira
    Feb 23, 2016
Loading...