K
Kerry Purdy
Hiya
I have 2 questions please.
Question1:
I have got myself a bit confused over the cost/use value. This is the text
I have but it doesn't seem to be correct/make sense in my brain:-
"For work resources, a per-use cost accrues each time that the resource is
used. For material resources, a per-use cost is accrued only once."
I have a 2-day job "Paint Ceiling"
I have a Painter (work) that charges £100 just to come to site + £10 per
hour (std=£10, cost/use=£100)
When assigned this is showing me:-
£260 cost for the task (£100 + 16 x £10) ??
I was expecting £360 ??
I have a Ladder (Material) that costs me £50 each time I use it (cost/use=£50)
When assigned this is showing me a cost of £50
I was expecting £100 ??
Perhaps I am using the wrong examples, thats why this issue doesn't make
sense in my mind. Can anyone shed any light on the matter please or give me
better examples. Perhaps there is a better way to manage the above costs.
Question 2: If I buy a ladder - it costs me £200 do i need to create a
ladder resource at £200 then another ladder resource costed at £0, the first
time I use the ladder use the costed one, from then on use the £0??
I hope this makes some sense to someone.
Thanks in advance for your help.
Kerry
I have 2 questions please.
Question1:
I have got myself a bit confused over the cost/use value. This is the text
I have but it doesn't seem to be correct/make sense in my brain:-
"For work resources, a per-use cost accrues each time that the resource is
used. For material resources, a per-use cost is accrued only once."
I have a 2-day job "Paint Ceiling"
I have a Painter (work) that charges £100 just to come to site + £10 per
hour (std=£10, cost/use=£100)
When assigned this is showing me:-
£260 cost for the task (£100 + 16 x £10) ??
I was expecting £360 ??
I have a Ladder (Material) that costs me £50 each time I use it (cost/use=£50)
When assigned this is showing me a cost of £50
I was expecting £100 ??
Perhaps I am using the wrong examples, thats why this issue doesn't make
sense in my mind. Can anyone shed any light on the matter please or give me
better examples. Perhaps there is a better way to manage the above costs.
Question 2: If I buy a ladder - it costs me £200 do i need to create a
ladder resource at £200 then another ladder resource costed at £0, the first
time I use the ladder use the costed one, from then on use the £0??
I hope this makes some sense to someone.
Thanks in advance for your help.
Kerry