Physical % Complete Calculation & Roll-Up

C

Cory Levine

I am having problems getting the “Physical % Complete†column to roll-up
properly from Detail Tasks to Summary Tasks.

First, a little background - I am using “Physical % Complete†to calculate
earned value and I have baselined my schedule. In some places in my
schedule, I have tasks defined at the fifth outline level; so I have many
sub-Summary Tasks to roll-up.

When I enter actuals for the Detail Tasks and manually enter values into the
“Physical % Complete†column, the values from the Detail Tasks do not
correctly roll-up to the Summary Task. For example, I have nine Detail tasks
beneath a Summary Task. When I specify that six of the Detail Tasks are 100%
complete, the Summary Task should calculate to show a value of about 67%.
Instead, it shows a value of 100%. Any ideas?

Also, not all sub-Summary Tasks are rolling-up to their parent Summary
Tasks. For example, I enter “Physical % Complete†values in the Detail Tasks
of a sub-Summary Task which roll-up (albeit incorrectly) to the sub-Summary
Task. However, the “Physical % Complete†value in that sub-Summary Task does
not roll-up at all to its parent Summary Task. Again, any ideas?
 
G

Gérard Ducouret

Hello Cory,
The "Physical % Complete" *never* rolls-up to Summary Tasks. As you said,
it's used to calculate Earned value. EV will roll-up to summary. Don't
confuse with the Percent Complete.

Gérard Ducouret
 
I

Ian Gray

Then why does it work sometimes and not others? I have the same issue - if
Physical % Complete *never* rolled up I wouldn't be concerned, but sometimes
it does, and sometimes it doesn't. Can you explain that?
Thanks
Ian
 
Joined
Jul 26, 2012
Messages
2
Reaction score
0
Physical % rollup

Hi Cory,

Physical % complete does roll up. However certain steps criteria must be met before it will:

1. project must be base lined
2. child tasks for the summary must have a resource & cost assigned to it
3. (most common cause of Physical % not rolling up) All the tasks must be set to "physical % complete". Do this by:

right click anywhere on field headings, insert column, choose "earned value method"
set all the tasks to physical % complete.

for future you can set the default "earned value method" in options:

in file tab, choose options, then advanced, in earned value options choose "physical % complete"
You may also choose which baseline the physical % complete is used calculations with some of the earned value type fields.

Hope this helps,
 
Joined
Jul 26, 2012
Messages
2
Reaction score
0
BTW Cory

my problem is exactly the same as yours, let me know if you find the problem.

I posted the last because I've seen alot of threads posted explaining that physical % complete field does not roll up.

found this article which may help but this forum will not allow me to provide a link:

find it by google "project Epistemology" then search "physical % complete" in their search box
 