C
CMG
I have a task (#205) which is a milestone with the date
of 7/3, a subsequent milesotne task (#209) is linked to
task 205. The relationahip is such that it is 205 + 10.
The date then calculates as 7/17, instead of 7/18. It
seems that Project is not counting July 4th as a holiday,
even though the project calendar has it as a non-working
day. Why is this?
Please help!
of 7/3, a subsequent milesotne task (#209) is linked to
task 205. The relationahip is such that it is 205 + 10.
The date then calculates as 7/17, instead of 7/18. It
seems that Project is not counting July 4th as a holiday,
even though the project calendar has it as a non-working
day. Why is this?
Please help!