Predecessors

S

Schalk

I have two subtasks that starts on 07/11/05 if i put a predessesor on the
second task it should update the start and end dates but it just stays the
same,please help.
ms project 2003
 
R

Rod Gill

Hi,

Does the second task have an actual start date or is calculation on manual?
If either, then it can't move. Set % Complete to 0% and test calculation by
pressing f9 to calculate.
 
M

Mike Glen

Hi Schalk ,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Options.../Calculation tab and set calculation to Automatic.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top