rms
Thanks for your response, even though it was not what I
was hoping for. Since you were kind enough to reply, I'll
tell what I do when I have as many as 15 or 20
Predecessors to a task (but it's time consuming and the
reason for my posting).
I create multiple tasks (for the task with numerous
Predecessors), at the same level and label
them "A", "B", "C", etc. Then I have the first 4 or 5
Predecessors listed for task "A": then task "A" and the
next 4 or 5 Predecessors are listed for task "B", etc.,
until I get all the Predecessors listed in a column of
reasonable width (that will print out all the
Predecessors).
If you, or anyone else has a better way, I sure would
appreciate it. Thanks.
RussDGTMFG