[Project 2013] More accuracy with resource, unit %, and cost?

Discussion in 'Project' started by cag8f, Feb 1, 2015.

  1. cag8f

    cag8f

    Joined:
    Feb 1, 2015
    Messages:
    1
    Likes Received:
    0
    Hi all.

    I'm just starting with MS Project, and am encountering an issue with costs. I have created a task and assigned one of my resources to the task. The resource will only commit a certain percentage of his time to the task. In my case, the duration of the task is 4 days, while the resource will only commit 2 hours to it. The percentage is then 2/96 = 2.08333%. But Project rounds that to 2%, resulting in a large (~25%) error in the calculated cost. Is there a way to carry this out more accurately?


    Thanks in advance.
     
    cag8f, Feb 1, 2015
    #1
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.