T
Trevor
Good day,
I have a problem setting up a task that has two resources
allocated to it from a separate resource file.
The task has been estimated for 52 hours, actual work is
25. I need the remaining hours complete by (let's say)
Feb. 24.
My problem is that it would appear that not all these
conditions/criteria are realized within in MS Project.
Although only 47% of the estimate is complete (actual
recorded resource hours), Project registers 100% complete
for the estimated 52 hours.
The second problem is that MS Project will not move the
finish date to Feb. 24, instead it lists the 19th.
How can I manipulate the task to finish on the 24th with
an estimated 52 hours and reflect that only 47% of the
task is actually completed?
BTW I have tried 'Must Finish On' as a constraint but the
problem still exists.
Trevor
I have a problem setting up a task that has two resources
allocated to it from a separate resource file.
The task has been estimated for 52 hours, actual work is
25. I need the remaining hours complete by (let's say)
Feb. 24.
My problem is that it would appear that not all these
conditions/criteria are realized within in MS Project.
Although only 47% of the estimate is complete (actual
recorded resource hours), Project registers 100% complete
for the estimated 52 hours.
The second problem is that MS Project will not move the
finish date to Feb. 24, instead it lists the 19th.
How can I manipulate the task to finish on the 24th with
an estimated 52 hours and reflect that only 47% of the
task is actually completed?
BTW I have tried 'Must Finish On' as a constraint but the
problem still exists.
Trevor