I want to use Microsoft Project to link individual tasks between a master file, and 4 sub project files. I believe I can do this by copying individual tasks from the sub projects and doing a 'paste special, paste link' to the master file. However, I get the following error message when I do this: "The OLE paste operation cannot be completed. The data that you are trying to paste is not valid for Project." Can anyone helping?