As Project progresses , new action/tasks may require and dates associated
with this tasks. How adding new tasks/dates will affect baseline and further
project tracking.
Example,
Task1 (saved as baseline) dates
subTask1 (saved as baseline) dates
new subTask2 dates (created as Project progresses)
new subTask3 dates (created as Project progresses)
Will subTask2 and subTask3 tracked against the baseline? or they will be
considered as baseline tasks?