B
bakkhos
I am new in using Project. I am running into a problem where I do not
know how to set up Project to calculate duration/time.
Here is my particular situation. My project have tasks that take from a
couple of minutes to actaully do or complete to a couple of hours.
However, it may take days before the tasks are actually delivered to
the client, since most of my team members worked on multiple projects
per day, the do not have 8hrs per day and 5 days a week to allocate for
this project. But in projects, if I were to use "hours" in my duration,
then I will not be able to see in my gantt chart the actual start date,
delivery dates or milestones in a calender. MS prokect will just
calaculate my dyation and show my gantt chart using the 8hr/day model.
It seems that Project asssumes that my tasks and my resource are have
8hrs/5days a week to complete this project, when in truth they have 8 to
10 other projects that they are working on in one particular day.
So how can I solve this issue? Is there a way for me to be able to
calculate the time it takes my resource to do a task in hours, and yet
also be able to show that the hours and days of completeion will be
different?
Please help. I've tried to read many postings, but none have addressed
this particular issue.
thank you.
Nancy
know how to set up Project to calculate duration/time.
Here is my particular situation. My project have tasks that take from a
couple of minutes to actaully do or complete to a couple of hours.
However, it may take days before the tasks are actually delivered to
the client, since most of my team members worked on multiple projects
per day, the do not have 8hrs per day and 5 days a week to allocate for
this project. But in projects, if I were to use "hours" in my duration,
then I will not be able to see in my gantt chart the actual start date,
delivery dates or milestones in a calender. MS prokect will just
calaculate my dyation and show my gantt chart using the 8hr/day model.
It seems that Project asssumes that my tasks and my resource are have
8hrs/5days a week to complete this project, when in truth they have 8 to
10 other projects that they are working on in one particular day.
So how can I solve this issue? Is there a way for me to be able to
calculate the time it takes my resource to do a task in hours, and yet
also be able to show that the hours and days of completeion will be
different?
Please help. I've tried to read many postings, but none have addressed
this particular issue.
thank you.
Nancy