JimC
I need clarification on the use of Options/Calculation
checkboxes as they relate to rescheduling "late" tasks.
Example: I have a task defined by 40 hours of work, to be
completed over 5 days between 9/20-9/24. current date
and status dates are 9/27. I have enabled the
Options/Calculation tab check box "Move start of remaining
parts before status date forward to status date".
After I record 20 hours actual work to the task,
the remaining 20 hours of work are still scheduled to be
completed by 9/24...I was anticipating the remaining work
would have been re-scheduled to begin on 9/27.
What am I missing?
checkboxes as they relate to rescheduling "late" tasks.
Example: I have a task defined by 40 hours of work, to be
completed over 5 days between 9/20-9/24. current date
and status dates are 9/27. I have enabled the
Options/Calculation tab check box "Move start of remaining
parts before status date forward to status date".
After I record 20 hours actual work to the task,
the remaining 20 hours of work are still scheduled to be
completed by 9/24...I was anticipating the remaining work
would have been re-scheduled to begin on 9/27.
What am I missing?