Hello,
In the Resource Sheet, copy the Resource Name column in the Initial column.
Then go back to the Gantt Chart :
Format / Bar Styles ..
Select a task bar (probably blue)
Click the Text tab
Replace Resource Names on the right side of the bar with Resource Initials.
Hope this helps,
Gérard Ducouret [Project MVP]