How do you request task status without Project Server in Project 2002? I set
"Collaborate using:" to Email only and added email addresses to the
resources, but when the email is set, it emails an attachment MSPJ.MTM which
can't be opened. Is there something else I need to change?
 
J

JulieS

Hi cyberlill,

Please see the following Knowledge Base Article on setting up workgroup
messaging in Project 2002:

http://support.microsoft.com/default.aspx?scid=kb;en-us;329827&Product=prj2002I hope this helps. Please let us know how you get along.Julie"cyberlill" <[email protected]> wrote in messageHow do you request task status without Project Server in Project 2002?I set> "Collaborate using:" to Email only and added email addresses to the> resources, but when the email is set, it emails an attachment MSPJ.MTMwhich> can't be opened. Is there something else I need to change?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top