S
Steve W.
We have one resource with 100% units who was scheduled to work on a fixed
units task for four hours. The four hours of scheduled work on the task also
had a duration of four hours.
The resource actually required 8 hours to complete the task and the Gantt
Chart showed her units to increase to 200%. In other words, Project assumed
the 8 hours were still done in the scheduled 4 hour duration. Essentially,
when the resource entered the 8 hours, Project treated the task like it was a
fixed duration task in that the work changed (from the scheduled 4 to the
actual 8) and therefore the units are re-calculated. The reality is that the
resource did not complete the 8 hour task in four hours, it took her all day.
Why doesn't Project adjust the duration and spread the 8 hours over the 8
hour day, which would be consistent with the resources's 100% availability
and with reality?
Any advice and information would be appreciated.
units task for four hours. The four hours of scheduled work on the task also
had a duration of four hours.
The resource actually required 8 hours to complete the task and the Gantt
Chart showed her units to increase to 200%. In other words, Project assumed
the 8 hours were still done in the scheduled 4 hour duration. Essentially,
when the resource entered the 8 hours, Project treated the task like it was a
fixed duration task in that the work changed (from the scheduled 4 to the
actual 8) and therefore the units are re-calculated. The reality is that the
resource did not complete the 8 hour task in four hours, it took her all day.
Why doesn't Project adjust the duration and spread the 8 hours over the 8
hour day, which would be consistent with the resources's 100% availability
and with reality?
Any advice and information would be appreciated.