drjayr2002
I am using a copy of an existing mpp, which has a 1000 tasks, and for high
level planning would like to look at only 10 tasks and concentrate on work at
that level, and start assigning resource at generic level like BA,SA,Dev and
QA to fine tune start and end dates of the project. Does Ms Project allows to
enter resources at group level or I need to create another MPP with these
tasks and play around with it? Any suggestions welcome. Regards, Jay