Hello all,
In some cases, in microsoft Project 2007, the resource allocation % is
not being correctly calculated.
This problem is created when a task that has both a predecessor and a
successor is changed by way of a resource submitting task updates in
PWA. The update must include hours for days that lie outside the
scheduled start and finish dates for the task. The task must be of
the Fixed Work type.
In some cases, the % allocation will jump up to 1200%. While the
units displayed in the resource column are incorrect, the planned work
(calculated based on the remaining hours and the fixed % allocation
(units)) is correct.
Any help on this issue would be appreciated.
Thanks,
Greg
In some cases, in microsoft Project 2007, the resource allocation % is
not being correctly calculated.
This problem is created when a task that has both a predecessor and a
successor is changed by way of a resource submitting task updates in
PWA. The update must include hours for days that lie outside the
scheduled start and finish dates for the task. The task must be of
the Fixed Work type.
In some cases, the % allocation will jump up to 1200%. While the
units displayed in the resource column are incorrect, the planned work
(calculated based on the remaining hours and the fixed % allocation
(units)) is correct.
Any help on this issue would be appreciated.
Thanks,
Greg