I have a Fixed Work task that I have allocated several resources to
work on. If Resource A's calendar is scheduled for 10 hours of work
during this task, I understand Resource A being 100% allocated when the
Resource Sheet shows 10 hours of work for Resource A. However, when I
allocate a second resource, say Resource B, several strange things are
happening that I do not yet understand:
1. Resource A shows as working less horus on the Resource Sheet, but
it is still shown as 100% allocated.
2. The duration of the task increases even though I have assigned more
resources to it.
Any pointers would be great, Thanks.
work on. If Resource A's calendar is scheduled for 10 hours of work
during this task, I understand Resource A being 100% allocated when the
Resource Sheet shows 10 hours of work for Resource A. However, when I
allocate a second resource, say Resource B, several strange things are
happening that I do not yet understand:
1. Resource A shows as working less horus on the Resource Sheet, but
it is still shown as 100% allocated.
2. The duration of the task increases even though I have assigned more
resources to it.
Any pointers would be great, Thanks.