resource calendars

J

jody@plains

I have to schedule a crew of 10 men to work for ten days then off for four
days, a repeating schedule. How do I set this up correctly??
 
G

Gérard Ducouret

In the resource Sheet, select this resource, then:
Tools / Change Working Time...
Select the column (M for Monday etc.) and set each colum as working or non
working

Gérard Ducouret
 
J

Jan De Messemaeker

Hi Gerard and all,

First, this way doesn't work in 2007 any more: it's become much more
elaborate.
But regardless, it doesn't help our poster who wants 4 days per fortnight,
so only half of the Sundays(f.i.) will be nonworking.

Supposing the 4 nonworking days are Th, Fr, Sa and Su, this is how you do it
in 2007:
Tools, Change working time
Select the resource from the calendars dropdown
Add a line to the exception list
Click Details
HIn the details form
Click nonworking time
Select the nonworking days
Select recur every 2 weeks
Be sure the span between Start and Finish is sufficient.

Hope this helps,




--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 