Hi Gerard and all,
First, this way doesn't work in 2007 any more: it's become much more
elaborate.
But regardless, it doesn't help our poster who wants 4 days per fortnight,
so only half of the Sundays(f.i.) will be nonworking.
Supposing the 4 nonworking days are Th, Fr, Sa and Su, this is how you do it
in 2007:
Tools, Change working time
Select the resource from the calendars dropdown
Add a line to the exception list
Click Details
HIn the details form
Click nonworking time
Select the nonworking days
Select recur every 2 weeks
Be sure the span between Start and Finish is sufficient.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional