Resource Leveling Multiple Resources on one task

Discussion in 'Project' started by Jonathan Law, Apr 12, 2017.

  1. Jonathan Law

    Jonathan Law

    Joined:
    Apr 12, 2017
    Messages:
    3
    Likes Received:
    0
    Hi I have an issue I have found with MS project. Im not sure if its me or the software.

    I have the following scenario.

    Calendar set to a standard 24 hrs. The tasks can be completed in order. This will be decided once on site. For this reason I havent set any predecessor / successor relationships. There are two areas where the resources will be working lets call them Area1 & Area2..

    Resources
    Elec - Max 6
    Area1 - Max 1
    Area2 - Max 1

    when I Level Resources Im expecting to see the area 1 tasks in parallel with area 2 but it doesnt seem to work. anyone else had similar issues please?

    Before Leveling
    upload_2017-4-12_20-50-8.png

    After Leveling
    upload_2017-4-12_20-50-45.png
     

    Attached Files:

    Jonathan Law, Apr 12, 2017
    #1