Resource Leveling Multiple Resources on one task

Joined
Apr 12, 2017
Messages
3
Reaction score
0
Hi I have an issue I have found with MS project. Im not sure if its me or the software.

I have the following scenario.

Calendar set to a standard 24 hrs. The tasks can be completed in order. This will be decided once on site. For this reason I havent set any predecessor / successor relationships. There are two areas where the resources will be working lets call them Area1 & Area2..

Resources
Elec - Max 6
Area1 - Max 1
Area2 - Max 1

when I Level Resources Im expecting to see the area 1 tasks in parallel with area 2 but it doesnt seem to work. anyone else had similar issues please?

Before Leveling
upload_2017-4-12_20-50-8.png


After Leveling
upload_2017-4-12_20-50-45.png
 

Attachments

  • upload_2017-4-12_20-48-45.png
    upload_2017-4-12_20-48-45.png
    27.4 KB · Views: 423

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top