K
kvidy
I use Project Professional 2003 WITHOUT the Project Server. I use a .mpp file
as a resource pool and link it to all my projects.
After scheduling of the projects, assigning resources and levelling them, I
specify deadline dates for every project. In the process of specifying
deadlines, resources become over-allocated. I go resource by resource to find
overallocations, and then specify overtime for each case of over-allocation
and for every resource over-allocated.
My questions are......
1. Is there a way by which MS Project automatically allocates 'overtime
work' for resources, based on availability/non-availablity of a particular
resource?
2. When freeing a particular resource, the overtime work does not get
re-calculated or re-allocated. Is there a way to do it automatically or does
it have to be done manually after tedious searching which is most cases may
turn out inaccurate?
3. When adding overtime manually to every over-allocated resource, is it
possible to specify overtime on a day-by-day basis for a task and resource
rather than let Project do the overtime allocation which is invariably not
the best solution?
For info (if this will help).... Options Used:
= I level resources within available slack. The others options in the
levelling options page is 'unchecked' except the 'available slack' option.
= I level on 'Priority, Standard'.
= I specify deadline for a task in the project and sometimes also constrain
it with a 'Finish no Earlier Than' or some other flexible constraint.
as a resource pool and link it to all my projects.
After scheduling of the projects, assigning resources and levelling them, I
specify deadline dates for every project. In the process of specifying
deadlines, resources become over-allocated. I go resource by resource to find
overallocations, and then specify overtime for each case of over-allocation
and for every resource over-allocated.
My questions are......
1. Is there a way by which MS Project automatically allocates 'overtime
work' for resources, based on availability/non-availablity of a particular
resource?
2. When freeing a particular resource, the overtime work does not get
re-calculated or re-allocated. Is there a way to do it automatically or does
it have to be done manually after tedious searching which is most cases may
turn out inaccurate?
3. When adding overtime manually to every over-allocated resource, is it
possible to specify overtime on a day-by-day basis for a task and resource
rather than let Project do the overtime allocation which is invariably not
the best solution?
For info (if this will help).... Options Used:
= I level resources within available slack. The others options in the
levelling options page is 'unchecked' except the 'available slack' option.
= I level on 'Priority, Standard'.
= I specify deadline for a task in the project and sometimes also constrain
it with a 'Finish no Earlier Than' or some other flexible constraint.