B
Bo
I'm using Project 2000. I am needing to identify by resource group any overallocations. Based on the nature of the projects it appears the easiest way to do this is to assign by groups not individuals. My thought process is to make resources such as Engineering, Testing, QC, etc. I have a couple of questions regarding this approach:
1. Would I change the max unit % in the Resource Sheet to correspond with the number of individuals in the Group. Such as if there are 10 Engineers the max unit % would be 1,000?
2. Is there a way then to show the amount of hours not tasked for the day/week?
I hope this makes sense. Thanking everyone in advance.
1. Would I change the max unit % in the Resource Sheet to correspond with the number of individuals in the Group. Such as if there are 10 Engineers the max unit % would be 1,000?
2. Is there a way then to show the amount of hours not tasked for the day/week?
I hope this makes sense. Thanking everyone in advance.