B
barbara.korte
Hi,
I have some issue with my resources.
I create a schedule, tasks, assign resources and publish it.
I have one task A with 4hours duration. If my resource report 4h of
work, all goes fine.
If my resource report more than 4h, 6h for example, he got
overallocated and duration keeps the same.
Should the duration not keep constant and change it to 6h and not
overallocate my resource?
I try it using with fixed units with and without effort driven and I
got the same result.
Thanks a lot.
I have some issue with my resources.
I create a schedule, tasks, assign resources and publish it.
I have one task A with 4hours duration. If my resource report 4h of
work, all goes fine.
If my resource report more than 4h, 6h for example, he got
overallocated and duration keeps the same.
Should the duration not keep constant and change it to 6h and not
overallocate my resource?
I try it using with fixed units with and without effort driven and I
got the same result.
Thanks a lot.