Resource Usage with Late Start & Late Finish

L

Lalit

Hi to all,

can anybody suggest me how to have the resource usage with late start & Late
finish dates in a programme. Currently we can have it with early start &
Early finish.

Any Masters of MSP may help me out???
 
J

Jan De Messemaeker

Hi,

Project, Project information, Schedule from Project finish may well give
what you want.
You can go back to normal afterwards.
Hope this helps,
 
L

Lalit

Thanks Jan,

Well I had already done it & Plotted the S-curve with late start & Late
finish, but the LS & ES curves seems to be quite nearer to each other than
the available floats in the activites. My program has three phases & for each
phase the ES & LS curves should meet somewhere in the program.

My program has 0% progress till now, hence I tried an innovative thing. I
copied all the dates in LS & LF cols into ES & EF Finish cols, then plotted
the graph. It shows the realistic bulge in the curve for all tha phases.

But I didn't understand the difference between the results. The souls have
been same. Any idea?
 
J

Jan De Messemaeker

Hi,

Well, I tried to answer your question, now you tell me that I din't answer a
different question.
I never thought about an S-curve, only about showing Resource Usage with
late dates.
And didn't it?
I'm not a mind reader so I can only answer the questions as they appear.
Greetings,
 
L

Lalit

Hi Jan,

Well you got me the right answer on the first occasion....but i guess u were
too angry to read my second question.....I didn't mean that way.

Cheers.
 