I'll try to make this as simple of a question that i can. I have 2 crews of
ten men working 10 days and taking 4 off, these 2 crews have rotating
schedules they work from 6AM to 6 PM. Do I enter this as 20 different
resources? If I am able i would like to enter 1 crew as 1 resource. How would
this best be done? I am new to project and am also looking for some
introductory classes and would like some suggestions.