Schedule a predecessor with lag using total days, not working day.

P

pyper72

I'm trying to schedule a deliverable that is due 15 calendar days after the
award date. Is there any way I can use a predecessor task that is the
contract award with a lag to schedule this? When I use a normal lag it uses
working days. I don't think I'll be able to change the calendar as it will
be going into project server where the calendar is fixed.
 
J

JulieS

Hi pyper72,
Set up the lag as 15ed for elapsed days. This will count 15 24-hour days
instead of 15 working days.

Hope this helps. Let us know how you get along.
Julie
 