D
Dick
Every once in while I get a wierd values returned in the schedule variance
(SV) field. Meaning it does not relate the to actual work performed. For
example a resource scheduled for 1 hour of work at $100/hr retruns a SV of
($9.29), when I entered 1 hour of acutal work. I am leaning toward the
Project Status and Current Date fields. How do these fields affect the SV
calculation? Is there something else I can look at that will tell me exactly
the data being used to calculate the SV?
(SV) field. Meaning it does not relate the to actual work performed. For
example a resource scheduled for 1 hour of work at $100/hr retruns a SV of
($9.29), when I entered 1 hour of acutal work. I am leaning toward the
Project Status and Current Date fields. How do these fields affect the SV
calculation? Is there something else I can look at that will tell me exactly
the data being used to calculate the SV?