Secrets of resource levelling with MS project (manually)?

L

Lauchlan M

Hi,

I wrote a schedule in MS project and allocated resources to it.

I then levelled it by

1. looking in the resource sheet for overallocated resources
2. using the resource graph to see where they are over-allocated
3. using the GANTT chart filtered by the resource to identify what the
multiple tasks the resource is allocated to are, and manually addressing it.

I find this effective (I think through the clashes and make the choices I
want) but tedious.

Other than the auto-levelling, are there other more effective approaches to
resource levelling in MS project?

Ideally, I'd like view that tells me what tasks a given resource at a given
point in time is allocated to, but MS Project does not seem to have that.
Does it?

Thx,

Lauchlan M
 
L

Lauchlan M

It is called the Resource Usage view.

Ta, thanks.

I was wondering what that one was for! <g>

Lauchlan M
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top