I have a project in the works that has a bit of a moving start date
(what project doesn’t) based on a ship’s operating schedule. So
summary project “Repair” starts shortly after the ship returns to
port. Right now it has a Must Start On constraint. I could use “Start
No Earlier Than” just as well. In either case I set the date to our
best estimate and update it as we are informed. All the tasks that
follow "Repair" are no problem but the preparations are confusing me a
little. I need to set several preparation tasks to start, or finish
in some cases, a certain period of time (days) before the Repair task
starts. I want to be able to change the Repair start date and have
all the Preparation tasks adjust accordingly.
As an experiment I set up Prep as a successor to Repair, Start to
Finish and a -4 day lag. This seems to work but it looks weird on the
Gantt. Is there another way to do this and is there any reasons not to
do it the way I have come up with?
thanks
Robert
(what project doesn’t) based on a ship’s operating schedule. So
summary project “Repair” starts shortly after the ship returns to
port. Right now it has a Must Start On constraint. I could use “Start
No Earlier Than” just as well. In either case I set the date to our
best estimate and update it as we are informed. All the tasks that
follow "Repair" are no problem but the preparations are confusing me a
little. I need to set several preparation tasks to start, or finish
in some cases, a certain period of time (days) before the Repair task
starts. I want to be able to change the Repair start date and have
all the Preparation tasks adjust accordingly.
As an experiment I set up Prep as a successor to Repair, Start to
Finish and a -4 day lag. This seems to work but it looks weird on the
Gantt. Is there another way to do this and is there any reasons not to
do it the way I have come up with?
thanks
Robert