Setting same work for similar tasks on different projects

M

Mary Anne A.

I have several tasks that are similar among different projects. If I refine
the work hours for a task on one project, I have to do the same for the other
projects. Depending on the task, I either do a search for those tasks or sort
and group the tasks and then paste the info across those same tasks. Is there
a different, more automatic way to do this? For example, is there a way I can
set a generic tasks with specific defaults and if I change it in one row,
it'll automatically change on all the other rows where I've used that task?
Basically, I want it to work similar to how the resources work relative to
the Gantt chart -- if you change the specific resource information, like the
resource name, the gantt chart info will automatically be updates.

Thanks in advance,
 
R

Rod Gill

There isn't that ability for Tasks, but you could write VBA code to do it
for you. You would need to define a process first, then automate it.
 
M

Mary Anne A.

Bummer...thanks for the response.

Rod Gill said:
There isn't that ability for Tasks, but you could write VBA code to do it
for you. You would need to define a process first, then automate it.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
 

Ask a Question

Want to reply to this thread or ask your own question?