Setting up Project for weekend project?

S

Steve C.

I want to set up a MS Project Gant chart to track a weekend project, so I
only want to show Saturday and Sunday as the working days. How do I hide
non-working hours on a MS Project Gantt Chart?
 
J

John

Steve C. said:
I want to set up a MS Project Gant chart to track a weekend project, so I
only want to show Saturday and Sunday as the working days. How do I hide
non-working hours on a MS Project Gantt Chart?

Steve,
Unfortunately time elements on the Gantt Chart cannot be "hidden". I
assume your overall project will be done over a number of weekends and
the best you can do is to use the "Go to selected task" icon on the
Standard toolbar to shift the Gantt. Just select the first task for the
weekend of interest and hit the icon - it's not what you want but it
will save some scrolling.

Hope this helps.
John
Project MVP
 