Start Date Not Calculating Correctly?

Joined
Oct 7, 2013
Messages
1
Reaction score
0
I am seeing strange results when trying to schedule some simple tasks in Project 2010.
I am trying to "back" schedule a task, by assigning lag time with a predecessor task. When I put in 0 duration, it schedules the start date correctly. However, when I put in a duration of more than one day, it seems to multiply the duration by 3 to calculate the start date. I do have some tasks at the end of my schedule with a 24 hour calendar, but the tasks I am having the problems with have no calendar associated with the task and the Std calendar associated with the resources.

If I put in a duration of 8 hrs instead of one day, it does calculate correctly. Where is the length of a day stored? I would have thought it went by the current calendar for that task. As noted, the resources for the task have the std 8 hour day (8am-12pm, 1pm-5pm). The task does not have a calendar, but even it I specifically assign the task the Std calendar, 1 day's duration still seems to equal 24 hours.

I have attached a .png doc with screenshots.

Can you tell me what I am doing wrong?
 

Attachments

  • MS Project Scheduling Problem.png
    MS Project Scheduling Problem.png
    75.1 KB · Views: 425
Last edited:

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top