I need to have a task ("cover task") that starts the same time as one task
("start task") and ends the same time as yet another task ("finish task").
If the start time changes in "start task" and/or the finish time changes in
"finish task", the start and finish time, and, of course, duration, of "cover
task" should change to match.
I've tried setting predecessors (SS and FF), but the duratoin of "cover
task" doesn't change.
This "cover task" is for a mentor who needs to be on the schedule as long as
the group of tasks are in progress. The mentor needs to be there from the
start to finish and I need the mentor's start, finish, and duration to change
whenever the start, finish, and/or duration of the group of tasks changes.
Can anyone tell me how to do this?
Thank you
("start task") and ends the same time as yet another task ("finish task").
If the start time changes in "start task" and/or the finish time changes in
"finish task", the start and finish time, and, of course, duration, of "cover
task" should change to match.
I've tried setting predecessors (SS and FF), but the duratoin of "cover
task" doesn't change.
This "cover task" is for a mentor who needs to be on the schedule as long as
the group of tasks are in progress. The mentor needs to be there from the
start to finish and I need the mentor's start, finish, and duration to change
whenever the start, finish, and/or duration of the group of tasks changes.
Can anyone tell me how to do this?