K
Kekko
Hi I would like to highlight the difference between planned and actual
start/finish dates.
What I realized is that when I put 100% completion over a task, the
actual dates become identical to the planned ones.
How should I obtain different values betweern them?
Thanks in advance
Kekko
start/finish dates.
What I realized is that when I put 100% completion over a task, the
actual dates become identical to the planned ones.
How should I obtain different values betweern them?
Thanks in advance
Kekko