I
Intotao
Hi Guys,
This is probably a pretty easy one for most of you out there but here goes.
I've looked everywhere and figure I must be doing something incredibly wrong
but can't figure it out. Any help would be graciously appreciated.
I have baseline start and finish and start and finish fields, also I have
status.
When my finish date is later than my baseline finish date shouldn't project
show that the project is late?
For example
Baseline Start Date:11/06/06
Baseline Finish Date: 11/08/06
Start date: 11/12/06
Finish date: 11/14/06
Status: On Schedule!!!
Clearly I'm not on schedule, but behind, yet Project disagrees with me and
I'm afraid if this keeps up, I'm going to have to hone my photoshop skills
here....:-(
A hand?
This is probably a pretty easy one for most of you out there but here goes.
I've looked everywhere and figure I must be doing something incredibly wrong
but can't figure it out. Any help would be graciously appreciated.
I have baseline start and finish and start and finish fields, also I have
status.
When my finish date is later than my baseline finish date shouldn't project
show that the project is late?
For example
Baseline Start Date:11/06/06
Baseline Finish Date: 11/08/06
Start date: 11/12/06
Finish date: 11/14/06
Status: On Schedule!!!
Clearly I'm not on schedule, but behind, yet Project disagrees with me and
I'm afraid if this keeps up, I'm going to have to hone my photoshop skills
here....:-(
A hand?