M
Michael Gwin
Find myself wondering lateley (or maybe wishing) that when I look at a task
that has several successors (like a key project item that many subprojects
are waiting for) why MS Project doesnt do a better job of highlighting the
impact of delaying that key project item.
For example, Im implementing several projects and many of them require the
buildout of a host server that it will have guests built onto. Say I have 5
of these projects. Im in a meeting faced with a delay in the buildout of the
host server. Im always nervous to push out that date knowing its also
pushing out 5 tasks lower in the plan. I normally have to look at the
successor numbers one by one, scroll to those tasks, analyze the impact, etc.
I find it very hard to be able to provide the impact "on the spot" to
challenge the delay...
So my questions are,
Does MS Project have some built in "what if" type functions?
Is there a way to filter one task and show all succeeding tasks?
Is there any way that MS Project shows the "ripple effect" of doing this.
Please help.
Mike
that has several successors (like a key project item that many subprojects
are waiting for) why MS Project doesnt do a better job of highlighting the
impact of delaying that key project item.
For example, Im implementing several projects and many of them require the
buildout of a host server that it will have guests built onto. Say I have 5
of these projects. Im in a meeting faced with a delay in the buildout of the
host server. Im always nervous to push out that date knowing its also
pushing out 5 tasks lower in the plan. I normally have to look at the
successor numbers one by one, scroll to those tasks, analyze the impact, etc.
I find it very hard to be able to provide the impact "on the spot" to
challenge the delay...
So my questions are,
Does MS Project have some built in "what if" type functions?
Is there a way to filter one task and show all succeeding tasks?
Is there any way that MS Project shows the "ripple effect" of doing this.
Please help.
Mike