D
draco664
Greetings all,
I have a dozen or so projects that I merge into a single summary
project file. Since each of the projects were developed with different
methodologies and standards, MSP tends to crash when I try to simply
link them into one file.
To get around this, I have essentially created a view within each
individual project file that shows selected summary tasks with all the
relevent information in the table. I then copy and paste the raw data
from the working project file into the summary file.
This works well enough for my purposes, but I've been asked if I can
add an overview section at the top of the summary project file.
Background:
Each individual project has tasks specific to various parts of the
SDLC - Develop, Build, Test, etc.
Currently, the summary project file is in this format:
--
Proj A1
- Summary of Develop tasks
- Summary of Build tasks
- Summary of Test tasks... etc.
--
Proj A2
- Summary of Develop tasks
- Summary of Build tasks
- Summary of Test tasks... etc.
--
Proj A3
Etc...
Now, the overview section at the top of the summary project file needs
to show the summary info for each of the Develop/Build/etc tasks from
each of the individual projects, like:
Proj A
- Summary of Develop tasks from Proj A1, Proj A2, etc.
- Summary of Build tasks from Proj A1, Proj A2, etc.
- etc.
Any ideas on how to attack this?
I was thinking of identifying each of the summary tasks at the Proj A#
level, and using a macro to calculate the overview summary tasks from
that, but I wanted to get a feel to see if there was an easier/more
efficient way of doing it.
Thanks in advance,
Chris
I have a dozen or so projects that I merge into a single summary
project file. Since each of the projects were developed with different
methodologies and standards, MSP tends to crash when I try to simply
link them into one file.
To get around this, I have essentially created a view within each
individual project file that shows selected summary tasks with all the
relevent information in the table. I then copy and paste the raw data
from the working project file into the summary file.
This works well enough for my purposes, but I've been asked if I can
add an overview section at the top of the summary project file.
Background:
Each individual project has tasks specific to various parts of the
SDLC - Develop, Build, Test, etc.
Currently, the summary project file is in this format:
--
Proj A1
- Summary of Develop tasks
- Summary of Build tasks
- Summary of Test tasks... etc.
--
Proj A2
- Summary of Develop tasks
- Summary of Build tasks
- Summary of Test tasks... etc.
--
Proj A3
Etc...
Now, the overview section at the top of the summary project file needs
to show the summary info for each of the Develop/Build/etc tasks from
each of the individual projects, like:
Proj A
- Summary of Develop tasks from Proj A1, Proj A2, etc.
- Summary of Build tasks from Proj A1, Proj A2, etc.
- etc.
Any ideas on how to attack this?
I was thinking of identifying each of the summary tasks at the Proj A#
level, and using a macro to calculate the overview summary tasks from
that, but I wanted to get a feel to see if there was an easier/more
efficient way of doing it.
Thanks in advance,
Chris