Dean thank-you for the information. The current project I have has 27
Engineering Tasks if I say they are all 100 % complete the progress of the
Summary Project line shows 23%. There are 121 total tasks in it. My boss
wants to weight this to say in our eyes it is 40% of project completion I
do
not think project can do that.
--
:
If you can settle for duration weighted tasks, you can set Summary tasks
to
display from Actual Start to Summary Progress. Besides the duration
weighting, though you will get the standard Finish minus Remaining
Duration,
so progress will be to 8:00 AM of the next task to be performed.
You need some custom code to get task weights in. The code below is for
all
tasks, resulting in 5:00 PM progress on the status date instead of the
next
task. In this formula, Number19 is a rollup of the sum of weighted actual
effort and Number20 is a rollup of what you should have completed as of
the
status date.
IIf([Actual Start]<>[Start] Or [Actual Finish]=[Finish],[Actual
Finish],IIf([Summary]=Yes,ProjDateAdd([Start],ProjDateDiff([Start],IIf([Finish]<[Status
Date],[Finish],[Status
Date]))*[Number19]/[Number20]),IIf([Duration]=[Remaining
Duration],[Actual
Start],ProjDateAdd([Actual Start],[Actual Duration]))))
:
Jim, Thanks for your quick answer. But does Project treat them as equal
percentage of the whole 20% Eng, 20% Purch, etc
--
:
Insert the project summary task. Tools/Options.... place a check
mark in the
show project summary task box.
Assuming you have separate summaries for Engineering, Purchasing,
Fabrication, Shipping and Installation you will get a duration
weighted
%Complete when you show the %Complete column. The project summary
task will
give you %Complete at the project level.
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
:
Is there a way to show the summary progress no matter how many
tasks are in
the summary weighed to the overall project progress?
Example
Engineering 40%
Purchacing 15%
Fabrication 20%
Shipping 10%
Instalation15%
I have told my boss no but need the profesionals input.
Thanks in advance for your help.