Summary Task % Complete

S

Stephen

My summary tasks are showing 0% complete, even though sub tasks are showing
100% complete. Have I missed selecting an option?
 
M

Mike Glen

Hi Stephen,

Welcome to this Microsoft Project newsgroup :)

Check Tools/Options.../Calculations tab that calculations is set to
Automatic. Or press F9 to calculate.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

Stephen

Many thanks Glen. I managed to solve the problem myself. If I use % of Work
Complete (instead of % Complete), the sub tasks roll-up into a summary task %
of Work Complete).

Thanks for your comments.
Stephen
 
M

Mike Glen

You're welcome, Stephen. Glad you solved your problem, and thanks for the
feedback :)

Mike Glen
MS Project MVP
 