I have a project with about 700 tasks in it. SOME of the summary/rollup
tasks do NOT show 100% even though all subtasks are 100% complete I have
tried changing the % complete to 100% but it automatically changes back to
99% complete when I click on okay. There are no special constraints and some
of the tasks update correctly. I have the options set to calculate
automatically and I have no outside dependencies.