I am using MS Project 2007 Standard. If a task has multiple predecessors, the
Task Drivers function doesn't show all the predecessors. Why?
 
D

Dale Howard [MVP]

wt --

Because that's just how it works. It shows you what is actually driving the
Start date of the selected tasks. Hope this helps.
 
W

wt

Dale,

Yes it helps.

Just to clarify it a bit more - if those predecessors all end at the same
date, then they will all show up in the "Task Drivers" pane, otherwise only
the "latest" predecessor will show up.