task info on bars in Gantt chart

S

swell estimator

I went to the help section about adding text to Gantt bars and got nowhere.

Isn't there a way to add of bit of the task info to the bar itself or next
to it or close to it? And if so is there a quick way to do it such as
copying and pasting?

thank you in advance - Chris
 
J

JulieS

Hi Chris,

If you want to add information to all bars try Format > Bar Styles.
Select the bar type (Task, Critical Task, etc.) and click the Text
tab at the bottom of the Bar Styles dialog box. From the Left Right
list, select the field which holds the information you want to show.
If the information is not already stored in an existing field (Work,
Duration, for example) you can add one of the spare Text fields to a
table, add information there and then choose that field to display
in the Gantt chart.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top